Mariposa VII, a 7-story multifamily project, fabricated at Douglass Colony's headquarters using FRAMECAD and shipped directly to the jobsite where the building was erected in a total of 40 working days.
This seven storey multifamily project was built in Denver, CO with two levels of podium and five upper levels of cold formed steel . Douglass Colony supplied the pre-panelized metal stud wall framing and offered a turn-key solution with diversified builders as the contracted drywaller.All 422 load-bearing wall panels for levels three through seven of this 7-story (five levels on two levels of podium) project was fabricated at Douglass Colony's headquarters in Commerce City using FRAMECAD and shipped directly to the jobsite where the building was erected in a total of 40 working days, including all wall panels, flooring systems, and detailing with concrete poured and cured.
A total of 131,700 lbs of steel was used
The building included a total of 422 panels. All panels were fabricated at the Douglass Colony headquarters in Commerce City, CO in the 6-inch profile.
Two levels of podium
Each level took only 7 days to complete - 2 days to assemble and erect the wall panels and 5 days dedicated to finalise the floor system, the detailing on the floor deck, and the concrete. First panel was set on June 21st, 2016 and panels were delivered in 2-week intervals after that (after concrete had completely dried on each level)
If you would like to learn more about Douglass Colony, click here.
Geared to attract local residents, Sagebrush is a 90-unit building nestled in the foothills of East Gros Ventre Butte and overlooking Flat Creek. Perfectly situated near downtown Jackson, Sagebrush aims to be one of the most popular complexes in the area — and a project Douglass Colony was proud to work on.
When FrameTech Systems outgrew their existing manufacturing facility, they knew it was time for a bigger, more flexible space. As experts in cold formed steel (CFS) construction, they also knew exactly which method they would use to bring that space to life. So how did their award-winning CFS facility come to fruition?
Having made the switch to FRAMECAD’s automated construction system in April 2016, prefabricated steel framing experts SBS Group have used their FRAMECAD system to make significant savings for their customers whilst delivering an accelerated construction process.
SBS Group are continuously working to deliver exceptional results for their customers in a fast and effective manner. The Langdon Apartments are another great example of their dedication to providing accurate, high quality Cold Formed Steel solutions.